Level 9 Refurbishment Works

Maintenance Project

Start Date:

July 23rd, 2024

Expexted Date of Completion:

September 6th, 2024

Area:

Level 9 on the South Tower Rooftop

Equiries

Please email Building Management at manager@ilk.net.au

A Bit About The Project

The project involves the comprehensive replacement of waterproofing materials on the Levle 9 Rooftop.

 

This essential maintenance is required to prevent water ingress into private and common areas on other floors.

Benefits:

  • Improved protection against water damage and leaks.

  • Enhanced longevity of the building's roofing system.

  • Maintenance of property value and aesthetic appeal.

Scope of Work:

  1. Site Preparation: Clearing and securing the work area to ensure safety and accessibility for contractors.

  2. Removal of Existing Waterproofing: Thorough removal of old waterproofing materials, including inspection for any underlying damage or deterioration.

  3. Surface Preparation: Cleaning and preparing the roof surface to ensure proper adhesion of new waterproofing materials.

  4. Application of New Waterproofing System: Applying high-quality waterproofing membranes or coatings designed to withstand weathering, UV exposure, and temperature fluctuations.

  5. Sealing and Finishing: Ensuring all joints, edges, and penetrations are properly sealed to prevent any potential water leakage.

  6. Quality Assurance: Conducting inspections throughout the project to verify compliance with specifications and industry standards.

  7. Safety Measures: Implementing safety protocols to protect both workers and residents during the project duration.

 

Timeline:

The project is scheduled to commence on 23rd of July and is expected to be completed by 6th of September. Timelines may be subject to weather conditions and unforeseen challenges.

 

Impact on Residents:

During the project, residents may experience temporary noise and restricted access to certain areas. However, we will minimise disruption as much as possible and provide regular updates on progress on this page.​

Project Updates

23rd July 2024

Works have commenced to remove existing flooring to provide access to for the waterproofers.  This is expected to completed by the 2nd of August.